Check same connection point
Depending on the connection situation, the generation plant and participants must be connected at the same point of interconnection. The map supports the initial assessment but does not replace a detailed review. Open vZEV map
Putting the 10% requirement into context
The production output of the participating installations must amount to at least 10% of the connected load of all participants. Installations with fewer than 500 operating hours per year are not taken into account.
Take metering infrastructure into account
Smart meters are required for the vZEV. Once the application has been approved, BKW installs any missing smart meters within three months.
Clarify authorised representation
A contact person represents the vZEV vis-à-vis BKW, coordinates consents, reports changes and is the central point of contact for technical and administrative queries.
Prepare internal billing
BKW provides 15-minute metering data in CSV or EBIX format, as well as an energy overview. The vZEV is responsible for regulating the internal distribution and billing of the locally used electricity.
Set realistic expectations
Specialist partners should explain that a vZEV remains dependent on the public grid, requires additional organisation and is only definitively confirmed after an official review.