Same connection point
Depending on the connection situation, the production facility and participants must be connected to the same connection point. The map and the check in the portal provide initial guidance on this.
At least 10 percent
The production capacity of the participating systems must amount to at least 10 percent of the connected capacity of all participants. Systems with fewer than 500 operating hours per year are not taken into account.
Smart metering systems required
Smart meters are required for a vZEV. Once an application has been approved, BKW will install any missing smart meters within three months.
Binding representation
A contact person represents the vZEV vis-à-vis BKW, reports changes three months in advance, and coordinates consents, conditions and billing.
Bill metering data yourself
BKW provides 15-minute measurement data in CSV or EBIX format, as well as an energy overview. The vZEV handles the internal billing of locally used electricity itself.
Testing, measurement and data
BKW provides information about the grid topology, checks the application, installs any missing smart meters, measures the vZEV internal electricity flows and bills for grid consumption and feed-in.
Agree and bill locally
Participants designate a contact person, confirm their participation digitally, consent to the sharing of metering data and arrange payment for locally sourced electricity or credits for locally sold solar power.