Claim back costs for reinforcing the connection line
If the connection line had to be reinforced when connecting a large energy generation plant, costs may be reimbursed under certain conditions.
What applies?
Reimbursement for the line section outside the plot
The refund concerns the reinforcement of the connection line between the plot boundary and the grid connection point.
When connecting a large energy generation system, it may be necessary to reinforce the connection cable. The costs for the cable section between the property boundary and the grid connection point can now be reclaimed using a reimbursement form after completion of the system. The reimbursement amounts to a maximum of CHF 50.00 per kW of installed capacity.
Process
From application to payout
You submit the application to BKW. The further review and reimbursement are carried out in coordination with Swissgrid.
BKW checks the information, supplements it if necessary and forwards the application to the national grid company Swissgrid. Swissgrid decides on the refund and pays the amount to BKW. BKW then passes the refund amount on to you.
Submit application
01
Submit application
You submit the application form for reimbursement with the required information and documents.
Audit by BKW
02
Audit by BKW
BKW checks the information and adds to it if necessary before the application is forwarded to Swissgrid.
Application to Swissgrid
03
Application to Swissgrid
BKW submits the application to Swissgrid. Swissgrid reviews the application and decides on the reimbursement.
Payment received
04
Payment received
Swissgrid pays the refund amount to BKW. BKW then pays the amount out to you.
Cost estimate
How much can the refund be?
The amount depends on the effective costs and the installed capacity of the system.
Costs for reinforcing the connection line between the parcel boundary and the grid connection point may be reimbursed. The maximum amount is CHF 50.00 per kW of installed capacity. Example: For a capacity of 70 kW, the maximum amount is CHF 3,500.
Application form
Application form
The table cannot yet be fully represented with the currently permitted Payload sections. The complete and binding content is available in Notion.
Frequently asked questions
Questions about the reimbursement of the connection line
Answers on requirements, TAG, connection line and payment.
Questions about the reimbursement for the connection line?
If you have any questions about the application, the requirements or the process, BKW will be happy to assist you. Once the complete application has been submitted, BKW will review the information and forward the application to Swissgrid.