Check shared building connection
All participating consumption points and the production facility must be located behind the same building connection point. This demarcation must be clearly clarified before planning and submission.
Plan meters and schematics cleanly
Private meters, ZEV meters, production metering and the metering scheme must be planned in a traceable manner. The existing BKW meters are generally dismantled in the ZEV.
Consider the 10% rule
The total production capacity must amount to at least 10% of the total consumption capacity of all participating end consumers.
Submit all documents completely
Installation notification, metering diagram, site plan and other required documents must be submitted in full and consistently. The application must be submitted at least three months before activation.
Explain billing and roles
End customers must understand that the ZEV acts towards BKW as a joint customer and manages internal billing, terms and responsibilities itself.
Assign contact person
A designated contact person represents the ZEV vis-à-vis BKW. They are the central point of contact for invoices, changes, technical queries and subsequent adjustments.