In an emergency, the distribution system operator may temporarily limit the output of individual installations.
BKW uses emergency control when this is necessary for safe grid operation – in particular to comply with voltage limits and to avoid local power interruptions. The measure is limited to exceptional cases and is used in a targeted, minimally invasive manner and only for as long as necessary.
Affected plants
Which installations need to be prepared?
Different technical requirements apply depending on the system type, capacity and key date.
The relevant date is the date on which the technical connection application (TAG) was submitted. The technical connection conditions applicable on the date the TAG was received apply.
Energy generation plants
PV and EEA systems
Power generation plants with an installed total capacity of more than 30 kW must be equipped with the necessary provisions for emergency control. Special requirements apply to plants from 300 kW.View technical requirements
Charging stations
Charging infrastructure over 3.7 kW
Charging stations with a total installed capacity of more than 3.7 kW are affected. Downstream of the same connection point, the system owner can determine how a control command is distributed to individual charging stations.Download Q&A
Heat pumps
Heat pumps over 3.7 kW
Heat pumps with a total installed capacity of more than 3.7 kW must comply with the requirements. For systems over 300 kW, the connection is assessed on a case-by-case basis.View TAB from 2026
Battery storage
Storage depending on output and operating mode
Battery storage systems are affected if they reach the power limits and are able to feed electricity into the grid. Storage systems from 300 kW are affected if they are able to feed electricity into the grid and/or draw electricity from the grid.View TAB from 2026
Technical implementation
Connection via telecontrol technology or relays
Depending on the installation, the connection to the emergency control system is made via a telecontrol connection to the central control centre of BKW or via a relay installed in the electricity meter. The grid connection customer is responsible for implementation downstream of the switching device – i.e. “behind the meter”.
Frequently asked questions
Questions about emergency control
Answers on TAG, responsibility, control commands and special cases.